What Is an RA Bill in Construction? Full Form and Example

A running account bill (RA bill) is an interim claim a contractor submits for work measured up to a particular date. It shows what was billed previously, what the contractor is claiming now, and the total to date.

RA bill full form and meaning

The full form of RA bill is running account bill. It is called a running account because the account between the contractor and the client stays open while the work goes on. Instead of waiting for the end of the job, the contractor bills at intervals, usually monthly or at agreed stages, for the work measured so far. The bills are numbered in sequence, for example RA-1, RA-2 and RA-3, and the last one is the final bill.

Each RA bill is set against the bills before it. For every item in the bill of quantities (BOQ), it shows three positions: what was billed previously, what is claimed in this bill, and the cumulative total to date.

A worked example

One BOQ item, terrace membrane laying, at an illustrative contract rate of ₹300/m². Earlier bills covered 80 m². A further 40 m² has been measured and certified for this period.

Terrace membrane laying at ₹300/m² (illustrative figures)
PositionQuantityWork value
Previously billed80 m²₹24,000
This bill (present)40 m²₹12,000
Cumulative to date120 m²₹36,000

The work value claimed in this bill is ₹12,000 because the earlier 80 m² was already billed. To check the cumulative figure, add the previous and present quantities: 80 + 40 = 120 m². The work values add up the same way: ₹24,000 + ₹12,000 = ₹36,000.

₹12,000 is the value of the work before applicable taxes and deductions. Tax is then added, and deductions such as TDS, retention or the recovery of an advance are made, as the contract and the law provide. What remains is the net amount payable on this bill.

Who certifies an RA bill?

The contract decides. Commonly the client’s engineer, architect or quantity surveyor checks the measurement and certifies the quantity, and payment follows the certified figure. If the certified quantity differs from the quantity claimed, the bill is corrected, and the next bill carries the certified cumulative position forward.

RA bill vs final bill

AspectRA billFinal bill
WhenAt intervals while work is in progressOnce, after the work is complete
CoversWork measured up to the bill dateThe total quantity of the whole contract
NatureAn interim claim, adjusted by later billsSettles the account between the parties
RetentionUsually deducted, as the contract providesReleased or settled as the contract provides

What an RA bill usually contains

See how Buildem One handles RA bills →

RA bill questions

What is the full form of RA bill?

RA bill stands for running account bill: an interim bill raised for the work measured up to a date, rather than once at the end of the contract. Each RA bill is set against the ones before it.

What do previous, present and cumulative mean on an RA bill?

Previous is the quantity and value already billed in earlier RA bills. Present is what this bill claims for the current period. Cumulative is the total to date, and it must equal previous plus present.

What is the difference between an RA bill and a final bill?

An RA bill is an interim claim made while the work is in progress, and later bills adjust it. The final bill is raised once the work is complete and settles the account for the whole contract, including retention as the contract provides.

Who certifies an RA bill?

Whoever the contract names, commonly the client's engineer, architect or quantity surveyor. They check the measurement and certify the quantity, and payment follows the certified figure.

Are taxes and deductions shown on an RA bill?

Usually, after the work value. Tax is added, and deductions such as TDS, retention or the recovery of an advance are made, as the contract and the applicable law provide. The result is the net amount payable on that bill.