What Is an RA Bill in Construction? Full Form and Example
A running account bill (RA bill) is an interim claim a contractor submits for work measured up to a particular date. It shows what was billed previously, what the contractor is claiming now, and the total to date.
RA bill full form and meaning
The full form of RA bill is running account bill. It is called a running account because the account between the contractor and the client stays open while the work goes on. Instead of waiting for the end of the job, the contractor bills at intervals, usually monthly or at agreed stages, for the work measured so far. The bills are numbered in sequence, for example RA-1, RA-2 and RA-3, and the last one is the final bill.
Each RA bill is set against the bills before it. For every item in the bill of quantities (BOQ), it shows three positions: what was billed previously, what is claimed in this bill, and the cumulative total to date.
A worked example
One BOQ item, terrace membrane laying, at an illustrative contract rate of ₹300/m². Earlier bills covered 80 m². A further 40 m² has been measured and certified for this period.
| Position | Quantity | Work value |
|---|---|---|
| Previously billed | 80 m² | ₹24,000 |
| This bill (present) | 40 m² | ₹12,000 |
| Cumulative to date | 120 m² | ₹36,000 |
The work value claimed in this bill is ₹12,000 because the earlier 80 m² was already billed. To check the cumulative figure, add the previous and present quantities: 80 + 40 = 120 m². The work values add up the same way: ₹24,000 + ₹12,000 = ₹36,000.
₹12,000 is the value of the work before applicable taxes and deductions. Tax is then added, and deductions such as TDS, retention or the recovery of an advance are made, as the contract and the law provide. What remains is the net amount payable on this bill.
Who certifies an RA bill?
The contract decides. Commonly the client’s engineer, architect or quantity surveyor checks the measurement and certifies the quantity, and payment follows the certified figure. If the certified quantity differs from the quantity claimed, the bill is corrected, and the next bill carries the certified cumulative position forward.
RA bill vs final bill
| Aspect | RA bill | Final bill |
|---|---|---|
| When | At intervals while work is in progress | Once, after the work is complete |
| Covers | Work measured up to the bill date | The total quantity of the whole contract |
| Nature | An interim claim, adjusted by later bills | Settles the account between the parties |
| Retention | Usually deducted, as the contract provides | Released or settled as the contract provides |
What an RA bill usually contains
- The contract or work order reference, the bill number and the period it covers
- Each BOQ item with its unit and rate
- Previous, present and cumulative quantity and amount for each item
- The total work value, then tax and deductions, and the net amount payable
- The measurement it rests on, so each quantity can be traced and checked